🇺🇸 Architect Registration Examination (ARE) · flashcards

Architect Registration Examination (ARE) Construction and Evaluation Flashcards

52 question-and-answer cards covering Construction and Evaluation as it is examined in Architect Registration Examination (ARE). 24 of them are printed below, taken from across the deck — no signup, no paywall on the preview.

52Cards in deck
24Free preview
16Syllabus topics
~233Chars per answer
FreePrice

24 sample cards from the Construction and Evaluation deck

Sampled from the end of the deck, so these are different cards from the ones shown on the syllabus page.

  1. What is retainage in progress payments?

    A percentage (commonly 5–10%) withheld from each progress payment by the owner to ensure the contractor completes the work and corrects deficiencies; it is released at or near completion.

  2. On what grounds may an architect withhold or nullify a certificate for payment?

    Defective work not remedied, third-party claims/liens, failure to pay subcontractors, reasonable evidence the work can't be completed for the unpaid balance, damage to the owner or another contractor, or persistent failure to carry out the work per the contract documents.

  3. What is a Change Order (CO) and what three things does it modify?

    A written instrument signed by the owner, contractor, and architect that authorizes a change in the work. It can adjust the (1) contract sum, (2) contract time, and (3) scope of the work; all three parties must agree.

  4. What is a Construction Change Directive (CCD) and how does it differ from a change order?

    A CCD is signed by the owner and architect (not the contractor) directing a change in the work prior to agreement on cost/time. It is used when the parties cannot agree on terms, allowing work to proceed while the adjustment is determined later.

  5. What is an Architect's Supplemental Instruction (ASI) and when is it appropriate?

    A minor change in the work issued by the architect that is consistent with the contract documents and involves no change in contract sum or time. Signed only by the architect; no owner/contractor signature required.

  6. Differentiate the three change instruments by who signs and cost/time impact: Change Order, CCD, ASI.

    Change Order: owner+contractor+architect, agreed cost/time change. CCD: owner+architect, cost/time disputed/pending. ASI: architect only, no cost/time change (minor change consistent with documents).

  7. What is the difference between Substantial Completion and Final Completion?

    Substantial Completion is when the work is sufficiently complete that the owner can occupy/use it for its intended purpose. Final Completion is when all work, including punch list items, is fully finished per the contract documents.

  8. List key legal/contractual consequences that are triggered by the date of Substantial Completion.

    Owner takes occupancy; warranties typically begin; retainage may be reduced; responsibility for security, utilities, insurance, and maintenance shifts to the owner; and statutory/contractual limitation periods often start to run.

  9. What is a punch list and when is it prepared?

    A list, prepared at substantial completion, of incomplete or deficient items the contractor must finish or correct before final payment. The architect (with the contractor) inspects to verify each item is resolved before certifying final completion.

  10. What documents/items must typically be submitted before Final Payment is certified?

    Completed punch list, contractor's affidavit that debts are paid, release of liens/waivers, consent of surety, warranties and guarantees, operation/maintenance (O&M) manuals, as-built (record) drawings, and certificate of occupancy.

  11. What is a certificate of occupancy and who issues it?

    A document issued by the local building official (authority having jurisdiction) certifying that the building complies with applicable codes and is safe to occupy for its intended use. It is required before lawful occupancy.

  12. Under AIA A201, what is the first required step (condition precedent) for resolving most disputes before litigation?

    The claim must first be referred to the Initial Decision Maker (IDM)—by default the architect—who renders an initial decision; many disputes then proceed to mediation before binding dispute resolution (arbitration or litigation).

  13. Compare mediation, arbitration, and litigation as dispute resolution methods.

    Mediation: non-binding, a neutral facilitates a voluntary settlement. Arbitration: binding (usually), a neutral arbitrator renders an enforceable decision privately, faster than court. Litigation: binding public court process, formal, slower, and appealable.

  14. Under AIA A201, what is the time limit for a contractor to submit a claim after the event giving rise to it?

    Within 21 days after the occurrence of the event or after the claimant first recognizes the condition giving rise to the claim, whichever is later.

  15. What is the difference between a claim and a change order?

    A change order is a mutually agreed modification of contract sum/time/scope. A claim is a demand or assertion by one party seeking an adjustment (in payment, time, or other relief) that has not been agreed upon and may proceed to dispute resolution.

  16. What is the architect's role as Initial Decision Maker (IDM) in claims?

    To render an initial, impartial decision on claims between owner and contractor (approve, reject, request more data, or suggest compromise). The IDM decision is a condition precedent to mediation; the architect must act impartially though paid by the owner.

  17. What three primary quality-control tools verify construction quality conforms to the documents?

    Submittal review (shop drawings/samples), mock-ups and field samples, and testing & inspection (special inspections, material testing) by independent agencies—plus the architect's site observations.

  18. What is a mock-up and what is its function in quality evaluation?

    A full-scale sample assembly built (in place or off-site) to establish the standard of quality and appearance for materials and workmanship. Approved mock-ups become the benchmark against which the actual installed work is judged.

  19. What is a special inspection and who performs it?

    Code-required inspection of specific construction elements (e.g., structural welding, concrete, soils, fire-resistive assemblies) performed by qualified independent special inspectors, reporting to the building official to verify code compliance.

  20. What is post-occupancy evaluation (POE) and why is it used in building performance assessment?

    A systematic assessment of a building's performance after occupancy—measuring how well it meets user needs and design goals (energy, comfort, function, satisfaction). It informs corrective actions and provides lessons learned for future projects.

  21. In building performance assessment, name common categories of performance measured.

    Energy use/efficiency, thermal comfort, indoor air quality, acoustics, lighting/daylighting, water use, occupant satisfaction/functionality, and durability/maintenance—often benchmarked against codes, design targets, or rating systems (e.g., LEED).

  22. What is the typical process for defect identification and remediation during the warranty/correction period?

    Defect is identified (observation, owner report, POE) → documented and notice given to contractor → cause investigated → contractor corrects nonconforming work within the one-year correction period under A201 → corrected work re-inspected and verified.

  23. Under AIA A201, what is the one-year correction period and how does it relate to warranty?

    For one year after substantial completion, the contractor must correct nonconforming work discovered and reported. This correction period is a specific contractual obligation and is not a limitation on the broader warranty or the owner's other legal remedies.

  24. What is the value of "lessons learned" and feedback integration at project closeout?

    Capturing what worked and what failed (cost, schedule, quality, coordination, RFIs, change orders) and feeding it back into firm standards, details, specifications, and future estimating improves quality and reduces repeated errors—turning each project into organizational knowledge.

What this deck covers

The Construction and Evaluation deck follows the Architect Registration Examination (ARE) Construction and Evaluation syllabus — 4 chapters and 16 topics — so questions land on material that is genuinely examinable rather than trivia around it. That works out to roughly 13.0 cards per chapter.

Answers are written to be recallable, not just readable — averaging about 233 characters, which is long enough to carry the reasoning and short enough to say out loud.

A deck like this earns its keep on the second and third pass. Read the syllabus first so you know the shape of the subject, then use the cards to find the specific facts that have not stuck.

Construction and Evaluation flashcards FAQ

How many Construction and Evaluation flashcards are in this Architect Registration Examination (ARE) deck?

52 cards. This page previews 24 of them, sampled evenly across the deck so you can judge the difficulty before installing anything.

Are these Architect Registration Examination (ARE) flashcards free?

Yes. The preview here is free to read with no signup, and the full 52-card deck is free inside the Examius app.

What do the Construction and Evaluation cards cover?

They follow the Architect Registration Examination (ARE) Construction and Evaluation syllabus — 4 chapters and 16 topics — so the questions track what is actually examinable.

How should I use these flashcards?

Read the syllabus first so you know the shape of the subject, then drill the deck. Examius schedules each card with spaced repetition, so cards you keep missing come back sooner and ones you know drift further apart.