🇮🇳 GATE Architecture & Planning · flashcards

GATE Architecture & Planning Common Flashcards

50 question-and-answer cards covering Common as it is examined in GATE Architecture & Planning. 24 of them are printed below, taken from across the deck — no signup, no paywall on the preview.

50Cards in deck
24Free preview
62Syllabus topics
~236Chars per answer
FreePrice

24 sample cards from the Common deck

Sampled from the end of the deck, so these are different cards from the ones shown on the syllabus page.

  1. In CPM/PERT network analysis, define the critical path.

    The critical path is the longest continuous path of activities through the network, determining the minimum project duration. Activities on it have zero float (slack); any delay delays the whole project.

  2. State the formula for the PERT expected (mean) activity time.

    $t_e = \dfrac{t_o + 4t_m + t_p}{6}$, where $t_o$ = optimistic, $t_m$ = most likely, and $t_p$ = pessimistic time estimates.

  3. Give the PERT formulas for the standard deviation and variance of an activity.

    Standard deviation $\sigma = \dfrac{t_p - t_o}{6}$ and variance $\sigma^{2} = \left(\dfrac{t_p - t_o}{6}\right)^{2}$.

  4. State the key differences between PERT and CPM.

    PERT is probabilistic (three time estimates), event-oriented, used for R&D / non-repetitive projects, focuses on time. CPM is deterministic (single time estimate), activity-oriented, used for repetitive/construction projects, and incorporates time–cost trade-offs (crashing).

  5. Define total float and free float in network scheduling.

    Total float = $LFT - EST - \text{duration}$ (= LST − EST): the time an activity can be delayed without delaying project completion. Free float is the delay possible without delaying the early start of the following activity.

  6. What is 'crashing' in CPM and what is the cost slope?

    Crashing is shortening project duration by adding resources to critical activities at extra cost. Cost slope $= \dfrac{\text{Crash cost} - \text{Normal cost}}{\text{Normal time} - \text{Crash time}}$, i.e., the extra cost per unit of time saved.

  7. Distinguish between an 'estimate' and a 'specification' in construction.

    An estimate is the calculated probable quantity and cost of materials, labour and works. A specification is a written description of the quality, type and workmanship of materials and methods to be used. Quantities come from estimates; quality from specifications.

  8. Name common methods of preparing a building cost estimate.

    Plinth area (built-up area) method, cubic content (volume) method, unit-base/service-unit method, and detailed/item-rate (quantity) estimate — the most accurate.

  9. What is the 'plinth area rate' method of estimation?

    Approximate estimate found by multiplying the plinth (built-up) area of the building by a current plinth area rate (cost per $\text{m}^2$) derived from similar completed projects. $\text{Cost} = \text{Plinth area} \times \text{rate}$.

  10. Distinguish detailed (general) specification from particular specification.

    Detailed/general specifications describe the quality, proportion and workmanship of each material and item generally. Particular specifications describe the specific method and materials for a particular item of a particular work in greater detail.

  11. List the main methods of measuring quantities: explain 'centre line' vs 'long wall–short wall' methods.

    In the centre-line method, the total centre-line length of walls is multiplied by cross-section to get quantities (deducting for junctions). In the long wall–short wall method, long walls are measured out-to-out and short walls in-to-in (or vice versa) and summed. Both give the same earthwork/masonry volume.

  12. What is a 'Council of Architecture' (COA) and the legal basis of professional practice for architects in India?

    The Council of Architecture (COA) is the statutory body constituted under the Architects Act, 1972, which regulates registration, education standards and professional conduct of architects in India. Only registered architects may use the title 'architect'.

  13. State key duties under architectural professional ethics / code of conduct.

    Maintain integrity and competence; act as a faithful adviser to the client; avoid conflicts of interest; not supplant another architect; charge fees per scale of charges and not engage in advertising/canvassing; uphold public safety and welfare.

  14. What is the conventional scale of professional fees (total) charged by an architect in India, and what are the broad work stages?

    Conventional total architect's fee is about $5\%$–$8\%$ of project cost, released in stages: concept design, preliminary/schematic, drawings/approval, working drawings & tender, and construction/site supervision.

  15. In structural terms, distinguish 'form-active', 'vector-active', 'surface-active' and 'section-active' structure systems (Engel's classification).

    Form-active: carry loads through their form (cables, arches). Vector-active: through axial members in tension/compression (trusses). Surface-active: through surface continuity (shells, plates, folded plates). Section-active: through bending of section (beams, frames, slabs).

  16. How does the relationship between form and structure differ for a cable, an arch and a beam under load?

    A cable works in pure tension and takes the funicular (catenary) shape of the load. An arch is the inverted funicular working in pure compression. A beam spans straight and resists load by internal bending (combined tension and compression across its section).

  17. What are the basic principles of earthquake (disaster) resistant building configuration?

    Regular, symmetric plan and elevation; light weight; low centre of gravity; short spans; continuous, redundant load paths; ductile detailing; avoid soft/weak storeys, re-entrant corners and torsional irregularity; strong-column/weak-beam design.

  18. Name structural measures used to make buildings earthquake resistant.

    Shear walls, cross/lateral bracing, ductile RC moment frames with confining reinforcement, base isolation (bearings), tuned mass / energy dampers, ductile detailing of joints, and bands/ties (plinth, lintel, roof) in masonry.

  19. What is base isolation in seismic design?

    Base isolation decouples the building from ground motion by introducing flexible bearings (e.g., elastomeric/lead-rubber or sliding bearings) between the superstructure and foundation, lengthening the natural period and reducing transmitted seismic forces.

  20. What are the requirements/characteristics of temporary structures (shelters) for post-disaster rehabilitation?

    Rapidly deployable, lightweight, low-cost, locally available/recyclable materials, easy to assemble/dismantle, climate-appropriate, providing safety, privacy and sanitation. Phases: emergency shelter, transitional (temporary) shelter, then permanent reconstruction.

  21. Define an ecosystem and distinguish natural from man-made (artificial) ecosystems.

    An ecosystem is a community of living organisms interacting with their non-living (abiotic) environment as a system. Natural ecosystems (forest, ocean, pond) self-regulate without human control; man-made ecosystems (cropland, aquarium, city) are created and maintained by humans and depend on human input.

  22. Define a food chain and trophic levels in ecological systems.

    A food chain is the linear transfer of energy/food from one organism to another. Trophic levels: producers (autotrophs) → primary consumers (herbivores) → secondary consumers (carnivores) → tertiary consumers → decomposers, each level being a feeding stage.

  23. State the ecological 10% law of energy transfer (Lindeman's law).

    Only about $10\%$ of the energy stored at one trophic level is transferred to the next; roughly $90\%$ is lost as metabolic heat. This limits food chains to about 4–5 trophic levels.

  24. Differentiate the ecological terms ecosystem, habitat, niche and biome.

    Habitat is the physical place an organism lives. Niche is its functional role/use of resources. Ecosystem is the community plus its abiotic environment. A biome is a large regional ecosystem type defined by climate and dominant vegetation (e.g., desert, tundra, tropical rainforest).

What this deck covers

The Common deck follows the GATE Architecture & Planning Common syllabus — 7 chapters and 62 topics — so questions land on material that is genuinely examinable rather than trivia around it. That works out to roughly 7.1 cards per chapter.

Answers are written to be recallable, not just readable — averaging about 236 characters, which is long enough to carry the reasoning and short enough to say out loud.

A deck like this earns its keep on the second and third pass. Read the syllabus first so you know the shape of the subject, then use the cards to find the specific facts that have not stuck.

Common flashcards FAQ

How many Common flashcards are in this GATE Architecture & Planning deck?

50 cards. This page previews 24 of them, sampled evenly across the deck so you can judge the difficulty before installing anything.

Are these GATE Architecture & Planning flashcards free?

Yes. The preview here is free to read with no signup, and the full 50-card deck is free inside the Examius app.

What do the Common cards cover?

They follow the GATE Architecture & Planning Common syllabus — 7 chapters and 62 topics — so the questions track what is actually examinable.

How should I use these flashcards?

Read the syllabus first so you know the shape of the subject, then drill the deck. Examius schedules each card with spaced repetition, so cards you keep missing come back sooner and ones you know drift further apart.