50 question-and-answer cards covering Planning, Estimation, and Tracking Progress as it is examined in Certified ScrumMaster (CSM). 24 of them are printed below, taken from across the deck — no signup, no paywall on the preview.

50Cards in deck
24Free preview
11Syllabus topics
~228Chars per answer
FreePrice

24 sample cards from the Planning, Estimation, and Tracking Progress deck

Sampled from the end of the deck, so these are different cards from the ones shown on the syllabus page.

  1. What is Affinity Estimation (affinity grouping)?

    A fast estimation method where the team silently sorts many backlog items along a spectrum from small to large (or into size buckets) by similarity, then assigns point/size values to the groups. It is well suited to estimating a large number of items quickly.

  2. What is the 'bucket system' of estimation?

    A scalable technique where predefined buckets (e.g., 0,1,2,3,5,8,13,20,...) are laid out and items are placed into the appropriate bucket through divide-and-conquer discussion, allowing hundreds of items to be sized rapidly.

  3. What is dot voting as used in estimation or prioritization?

    A technique where participants distribute a limited number of dots/votes across items to express relative size or priority; totals reveal group consensus. It is quick but coarse.

  4. What is the difference between an estimate and a forecast?

    An estimate is an approximation of the size or effort of a specific item or piece of work; a forecast is a probabilistic projection of future outcomes (e.g., what will be done by a date) derived from estimates plus empirical data like velocity. Estimates are inputs; forecasts are outputs.

  5. Why does Scrum favor the word 'forecast' over 'commitment' for sprint scope?

    Because work is done under uncertainty; the Sprint Backlog is the Developers' best prediction of what they can complete, not a guaranteed contract. The 2011 Scrum Guide deliberately changed 'commitment' to 'forecast' to reflect empirical reality.

  6. What does it mean that Agile estimates are probabilistic, not deterministic?

    They express likelihood rather than certainty; completion can be stated as a range or confidence level (e.g., '80% chance done by sprint 6') because variability and unknowns make any single exact date unreliable.

  7. What is the cone of uncertainty in estimation?

    A model showing that estimates are least accurate at a project's start and progressively narrow (become more accurate) as work proceeds and knowledge increases. It justifies re-forecasting frequently rather than locking early estimates.

  8. What is velocity in Scrum?

    The amount of work, measured in story points (or items) of completed, 'Done' Product Backlog items, that a team finishes per sprint. It is an empirical, team-specific measure used to forecast future capacity.

  9. How is velocity calculated for a sprint?

    Velocity = sum of the estimated points of all backlog items that fully meet the Definition of Done within the sprint. Partially completed items count zero; only fully finished work is included.

  10. How is average velocity typically determined, and why use an average?

    By averaging the velocities of the last several completed sprints (often the last 3 or more). Averaging smooths sprint-to-sprint variation, giving a more reliable basis for forecasting than any single sprint.

  11. Why should velocity NOT be used to compare two different teams?

    Because story points are relative and calibrated independently by each team, a 5-point story for one team is not the same as a 5 for another. Velocity is meaningful only for forecasting within the same team.

  12. Why is velocity considered a planning/forecasting tool rather than a performance metric?

    It measures a team's empirical delivery rate to forecast capacity, not how 'good' the team is. Using it as a performance target invites point inflation and gaming, undermining its forecasting value.

  13. Should partially completed work be counted in velocity? Why or why not?

    No. Only items meeting the Definition of Done count, because Scrum values working, potentially releasable increments. Counting partial work would inflate velocity and produce unreliable forecasts.

  14. What is a Sprint Burndown chart and what does it track?

    A chart that plots the remaining work (typically Sprint Backlog effort in hours or points) on the vertical axis against time/days in the sprint on the horizontal axis, trending downward toward zero as work is completed. It tracks progress within a single sprint.

  15. On a burndown chart, what do the axes and the ideal line represent?

    X-axis = time (days of the sprint or sprints of a release); Y-axis = remaining work (hours or story points). The ideal line is a straight diagonal from total work to zero; the actual line shows real remaining work, and being above the ideal line signals being behind.

  16. What is a Release Burndown chart?

    A chart tracking remaining work (story points) across multiple sprints toward a release, with the Y-axis as remaining backlog points and X-axis as sprints. It shows whether the team is on pace to finish the release scope by the target sprint.

  17. What is a Burnup chart and how does it differ from a burndown chart?

    A burnup chart plots completed work rising over time toward a total-scope line. Unlike a burndown (which shows only remaining work), a burnup separates two lines, work completed and total scope, so scope changes are visible distinctly from progress.

  18. What key advantage does a burnup chart have over a burndown chart?

    It makes scope changes explicit: because the total-scope line is drawn separately, added or removed work is clearly visible, whereas on a burndown a scope increase can be mistaken for lack of progress (a flat or rising remaining line).

  19. On a burndown chart, what does a flat (horizontal) line indicate?

    No net reduction in remaining work, either no work was completed, or completed work was offset by newly added/discovered scope. It signals a stall or scope growth that should be investigated.

  20. What does it mean if the actual line on a sprint burndown is below the ideal line?

    The team is ahead of schedule, less work remains than the ideal trajectory predicts at that point, indicating it may finish early or could take on more work.

  21. How can a trend line on a release burndown/burnup be used to forecast completion?

    By extending the slope of completed work (or remaining-work reduction) as a trend line, you can project the sprint/date at which work will reach zero (burndown) or meet the scope line (burnup), giving a data-driven completion forecast.

  22. What is a Cumulative Flow Diagram (CFD) and what does it reveal?

    A stacked area chart showing the number of work items in each workflow state over time (e.g., To Do, In Progress, Done). The band widths reveal work-in-progress levels and bottlenecks, and the horizontal gap between bands approximates lead/cycle time.

  23. State Little's Law as a forecasting tool and what it relates.

    Little's Law: Average Cycle Time = Average Work In Progress (WIP) divided by Average Throughput. It relates how long items take to how much work is in progress and the completion rate, implying that reducing WIP shortens cycle time.

  24. What is empirical progress measurement in Scrum, and what counts as real progress?

    Measuring progress based on observed, actual outcomes, specifically working, 'Done' increments delivered, rather than on plans, percent-complete estimates, or effort spent. Empiricism rests on transparency, inspection, and adaptation, so only validated working software signals true progress.

What this deck covers

The Planning, Estimation, and Tracking Progress deck follows the Certified ScrumMaster (CSM) Planning, Estimation, and Tracking Progress syllabus — 3 chapters and 11 topics — so questions land on material that is genuinely examinable rather than trivia around it. That works out to roughly 16.7 cards per chapter.

Answers are written to be recallable, not just readable — averaging about 228 characters, which is long enough to carry the reasoning and short enough to say out loud.

A deck like this earns its keep on the second and third pass. Read the syllabus first so you know the shape of the subject, then use the cards to find the specific facts that have not stuck.

Planning, Estimation, and Tracking Progress flashcards FAQ

How many Planning, Estimation, and Tracking Progress flashcards are in this Certified ScrumMaster (CSM) deck?

50 cards. This page previews 24 of them, sampled evenly across the deck so you can judge the difficulty before installing anything.

Are these Certified ScrumMaster (CSM) flashcards free?

Yes. The preview here is free to read with no signup, and the full 50-card deck is free inside the Examius app.

What do the Planning, Estimation, and Tracking Progress cards cover?

They follow the Certified ScrumMaster (CSM) Planning, Estimation, and Tracking Progress syllabus — 3 chapters and 11 topics — so the questions track what is actually examinable.

How should I use these flashcards?

Read the syllabus first so you know the shape of the subject, then drill the deck. Examius schedules each card with spaced repetition, so cards you keep missing come back sooner and ones you know drift further apart.