Association for Project Management Qualification (APM PMQ) Risk, Issue and Change Management Flashcards
59 question-and-answer cards covering Risk, Issue and Change Management as it is examined in Association for Project Management Qualification (APM PMQ). 24 of them are printed below, taken from across the deck — no signup, no paywall on the preview.
24 sample cards from the Risk, Issue and Change Management deck
Sampled from the end of the deck, so these are different cards from the ones shown on the syllabus page.
What information is typically recorded in an issue register?
Issue ID, date raised, raised by, description, impact/severity, priority, owner, agreed actions, escalation route/status, target resolution date, and current status.
What is an escalation route in issue management?
A predefined path for raising an issue to a higher level of authority (e.g. project manager to sponsor/steering group) when it falls outside the current manager's delegated tolerance or authority to resolve.
Why are escalation routes important for issue management?
They ensure issues exceeding a manager's delegated authority/tolerance are passed promptly to those who can decide and act, preventing delay and ensuring decisions are taken at the right level.
What role does the project manager play in managing issues?
Owns the issue management process, ensures issues are logged and assessed, resolves those within their authority, escalates those beyond it, and reports issue status to the sponsor and stakeholders.
What role does the sponsor play in managing issues?
Takes decisions on escalated issues that exceed the project manager's authority or tolerances, provides direction and resources, and owns the business case affected by major issues.
Define change control.
The process through which all requests to change the baseline scope, deliverables, time or cost of a project are captured, evaluated, approved or rejected, and (if approved) implemented in a controlled way.
Why is change control necessary on a project?
To prevent uncontrolled change (scope creep), ensure changes are properly assessed for impact on the business case/objectives, maintain baseline integrity, and ensure decisions are authorised and documented.
List the typical steps of the change control process.
1) Request/capture change, 2) Log it, 3) Assess impact (cost, time, scope, quality, risk), 4) Recommend, 5) Decision (approve/reject/defer) by the appropriate authority, 6) Implement and update baseline/plans, 7) Review and close.
What is a change request?
A formal proposal to alter the project, documenting what change is sought, the reason/justification, and originator details, submitted for assessment and a decision through the change control process.
What is the change log (change register)?
A document that records all change requests and their status — including description, impact assessment, decision (approved/rejected/deferred), date and owner — providing an audit trail of changes.
Who typically authorises changes in change control?
The change authority — within delegated tolerances this may be the project manager; changes exceeding those tolerances (e.g. affecting the business case) are decided by the sponsor or a change control board.
What is a change control board (change authority)?
A group or nominated individual with delegated authority to review change requests and decide whether to approve, reject or defer them, especially those beyond the project manager's tolerance.
What is the project manager's role in change control?
To operate the process: ensure changes are logged and impact-assessed, approve changes within delegated authority, escalate larger changes to the sponsor/board, and update baselines and plans for approved changes.
Define configuration management.
The technical and administrative process of identifying, documenting, controlling, tracking the status of, and verifying the project's products (configuration items) and their versions throughout the life cycle.
List the main activities of configuration management.
Planning, identification (of configuration items), control (of versions/changes), status accounting (recording state), and verification/audit (confirming items match records).
What is a configuration item?
A product, deliverable or component (or a coherent group) that is treated as a single entity for configuration management purposes, with its own identification, baseline and version control.
What is 'status accounting' in configuration management?
Recording and reporting the current and historical state of each configuration item — its version, baseline and change history — so the status of all products is known at any time.
What is a configuration audit/verification?
A check that the actual configuration items match their records/specifications and that all changes have been properly authorised and recorded, ensuring integrity of the products.
What is the relationship between change control and configuration management?
Change control authorises whether a change happens; configuration management tracks and records the products and their versions affected by that change. Configuration management maintains the baseline that change control protects and updates.
How do change control and configuration management work together when a change is approved?
Change control approves the change, then configuration management updates the version/baseline of the affected configuration items and records the new status, keeping product records accurate and traceable.
What is a 'baseline' in this context?
A reference version of a plan, deliverable or configuration item that is fixed and agreed at a point in time, against which progress and any subsequent changes are measured and controlled.
Why must risk, issue and change processes be linked?
Because they overlap: a materialised risk becomes an issue, and resolving an issue or risk often requires a change. Linking them ensures consistent tracking, accountability and impact assessment across the project.
What is 'risk appetite' versus 'risk tolerance'?
Risk appetite is the amount of risk an organisation is willing to seek or accept in pursuit of objectives; risk tolerance is the threshold/boundary of acceptable variation around objectives before action or escalation is required.
Give two reasons issues should be escalated rather than resolved locally.
The issue exceeds the project manager's delegated authority or tolerance, or it requires resources, decisions or business-case changes that only the sponsor/governance board can authorise.
What this deck covers
The Risk, Issue and Change Management deck follows the Association for Project Management Qualification (APM PMQ) Risk, Issue and Change Management syllabus — 3 chapters and 15 topics — so questions land on material that is genuinely examinable rather than trivia around it. That works out to roughly 19.7 cards per chapter.
Answers are written to be recallable, not just readable — averaging about 200 characters, which is long enough to carry the reasoning and short enough to say out loud.
A deck like this earns its keep on the second and third pass. Read the syllabus first so you know the shape of the subject, then use the cards to find the specific facts that have not stuck.
Risk, Issue and Change Management flashcards FAQ
How many Risk, Issue and Change Management flashcards are in this Association for Project Management Qualification (APM PMQ) deck?
59 cards. This page previews 24 of them, sampled evenly across the deck so you can judge the difficulty before installing anything.
Are these Association for Project Management Qualification (APM PMQ) flashcards free?
Yes. The preview here is free to read with no signup, and the full 59-card deck is free inside the Examius app.
What do the Risk, Issue and Change Management cards cover?
They follow the Association for Project Management Qualification (APM PMQ) Risk, Issue and Change Management syllabus — 3 chapters and 15 topics — so the questions track what is actually examinable.
How should I use these flashcards?
Read the syllabus first so you know the shape of the subject, then drill the deck. Examius schedules each card with spaced repetition, so cards you keep missing come back sooner and ones you know drift further apart.