🇺🇸 Journeyman/Master Electrician License Exam · subject

Journeyman/Master Electrician License Exam National Electrical Code Navigation and General Requirements Syllabus

The National Electrical Code Navigation and General Requirements syllabus for Journeyman/Master Electrician License Exam in full: 4 chapters, 15 topics and 36 sub-topics, every one listed below, plus 61 National Electrical Code Navigation and General Requirements flashcards with answers.

4Chapters
15Topics
36Sub-topics
61Flashcards

National Electrical Code Navigation and General Requirements syllabus: all 4 chapters

Expand any chapter to see its topics and sub-topics.

  1. Code Structure and Administration

    4 topics
    • Layout of the NEC
      • Chapters 1-9, annexes, and how they interrelate
      • Articles, parts, sections, and tables
      • Using the index and table of contents efficiently
    • Definitions (Article 100)
      • Key terms: dwelling unit, accessible, in sight from, qualified person
      • Listed, labeled, identified, and approved
    • General Requirements (Article 110)
      • Working space about equipment (Table 110.26)
      • Equipment marking, terminations, and torque
      • Available fault current and arc-flash labeling
    • Mandatory Rules, Permissive Rules, and Explanatory Material
      • Interpreting 'shall' vs. 'shall be permitted'
      • Role of informational notes
  2. Branch Circuits, Feeders, and Outlets

    4 topics
    • Branch Circuit Ratings and Classifications (Article 210)
      • Permissible loads on 15, 20, 30, 40, and 50 amp circuits
      • Multiwire branch circuits and handle ties
      • Continuous loads and the 125% rule
    • Required Receptacle and Lighting Outlets
      • Dwelling small-appliance, laundry, and bathroom circuits
      • Receptacle spacing along walls and countertops
      • GFCI and AFCI required locations
    • Feeders (Article 215)
      • Minimum feeder size and ampacity
      • Feeder equipment grounding conductor sizing
    • Outside Branch Circuits and Feeders (Article 225)
      • Clearances over roofs and grade
      • Disconnects for separate buildings
  3. Services and Overcurrent Protection

    3 topics
    • Service Conductors and Equipment (Article 230)
      • Number of services and service disconnect rules
      • Service-entrance clearances and drip loops
      • Service disconnect grouping (six-handle / emergency disconnect)
    • Overcurrent Protection (Article 240)
      • Standard ampere ratings and the next-size-up rule
      • Tap rules (10-foot and 25-foot taps)
      • Overcurrent device location and accessibility
    • Conductor Ampacity and the Small-Conductor Rules
      • Small-conductor protection (240.4(D))
      • Series-rated vs. fully-rated systems
  4. Grounding and Bonding

    4 topics
    • System and Equipment Grounding (Article 250)
      • Grounded vs. grounding conductors
      • Main bonding jumper and system bonding jumper
    • Grounding Electrode System
      • Permitted electrodes and the 25-ohm rule
      • Grounding electrode conductor sizing (Table 250.66)
    • Equipment Grounding Conductor Sizing
      • Table 250.122 application
      • Upsizing EGC for voltage-drop-adjusted conductors
    • Bonding of Services and Metal Piping
      • Bonding around concentric/eccentric knockouts
      • Bonding metal water and gas piping systems

Journeyman/Master Electrician License Exam National Electrical Code Navigation and General Requirements flashcards — 61 questions with answers

  1. In what general organizational order is the National Electrical Code (NEC) laid out, from the introduction to the appendices?

    It starts with Article 90 (Introduction), then nine Chapters: Chapters 1-4 are general (apply to all installations), Chapters 5, 6, and 7 are special (occupancies, equipment, conditions), Chapter 8 covers communications systems (independent unless a rule references Chapters 1-7), and Chapter 9 contains tables. Informative Annexes (A-J) follow but are not enforceable.

  2. What is the purpose of NEC Article 90, and is it itself an enforceable part of the Code?

    Article 90 is the Introduction. It states the Code's purpose (the practical safeguarding of persons and property from electrical hazards), its scope, arrangement, and how it is to be enforced and applied. It is enforceable text, not merely commentary.

  3. Per Article 90.1, the NEC is described as a safety standard but NOT what two things?

    It is not intended as a design specification and not intended as an instruction manual for untrained persons. Compliance plus proper maintenance results in an installation that is essentially free from hazard but not necessarily efficient, convenient, or adequate for good service or future expansion.

  4. What is the difference between a mandatory rule and a permissive rule in the NEC, and what signal words identify each?

    A mandatory rule states an action that is required or prohibited and uses the words 'shall' or 'shall not.' A permissive rule describes options or alternatives that are allowed but not required, using 'shall be permitted' or 'shall not be required.'

  5. What is explanatory material in the NEC, how is it identified, and is it enforceable?

    Explanatory material appears as Informational Notes (formerly Fine Print Notes). It is identified by being labeled 'Informational Note' and is intended for clarification or reference only. It is NOT enforceable as a requirement.

  6. Article 100 defines a 'receptacle.' What is the NEC definition?

    A receptacle is a contact device installed at an outlet for the connection of an attachment plug (or for the direct connection of electrical utilization equipment designed to mate with the corresponding contact device). A single receptacle is one contact device with no other on the same yoke; a duplex (multiple) receptacle has two or more on the same yoke.

  7. Per Article 100, what is an 'outlet'?

    An outlet is a point on the wiring system at which current is taken to supply utilization equipment. (Compare to a receptacle, which is the device installed at an outlet.)

  8. How does Article 100 distinguish a 'branch circuit' from a 'feeder'?

    A branch circuit is the circuit conductors between the final overcurrent device protecting the circuit and the outlet(s). A feeder is all circuit conductors between the service equipment (or the source of a separately derived system, or other power supply source) and the final branch-circuit overcurrent device.

  9. Per Article 100, what is the precise definition of the 'service point'?

    The service point is the point of connection between the facilities of the serving utility and the premises wiring. It marks the dividing line between utility-owned conductors and the premises wiring covered by the NEC.

  10. Article 100 defines 'ampacity.' What is it?

    Ampacity is the maximum current, in amperes, that a conductor can carry continuously under the conditions of use without exceeding its temperature rating.

  11. What is a 'continuous load' as defined in Article 100, and why does it matter?

    A continuous load is a load where the maximum current is expected to continue for 3 hours or more. It matters because branch-circuit and feeder conductors and overcurrent devices supplying continuous loads must generally be sized at 125% of the continuous load (i.e., the load is limited to 80% of the device rating).

  12. Per Article 110.3(B), what is the rule regarding listed and labeled equipment?

    Listed or labeled equipment must be installed and used in accordance with any instructions included in the listing or labeling. Deviating from those instructions is an NEC violation.

  13. What are the required minimum working clearances (depth) in front of electrical equipment 0-150 V to ground per Table 110.26(A)(1) for Conditions 1, 2, and 3?

    For 0-150 V to ground: Condition 1 = $0.9\text{ m}$ ($3\text{ ft}$), Condition 2 = $0.9\text{ m}$ ($3\text{ ft}$), Condition 3 = $0.9\text{ m}$ ($3\text{ ft}$). (At this voltage range all three conditions require 3 ft.)

  14. Per Article 110.26, what minimum width and height must be maintained for the working space about electrical equipment likely to be examined or serviced while energized?

    The working space width must be the width of the equipment or $762\text{ mm}$ ($30\text{ in}$), whichever is greater, and must permit a 90-degree door opening. The headroom (height) must be at least $2.0\text{ m}$ ($6.5\text{ ft}$) or the height of the equipment, whichever is greater.

  15. Per Article 110.14(C), what governs the temperature rating used for conductor ampacity at terminations?

    Conductor ampacity at a termination is limited by the lowest temperature rating of any connected termination, conductor, or device. For equipment rated 100 A or less (or marked for #14-#1 conductors), terminations are generally rated 60°C unless marked otherwise; for over 100 A, generally 75°C, unless the equipment is listed and marked for a higher temperature.

  16. What three standard nominal voltages or system arrangements does Article 110 require the available short-circuit current and equipment to be capable of withstanding (interrupting/short-circuit current rating)?

    Per 110.9 (interrupting rating) and 110.10 (circuit impedance/short-circuit ratings), equipment intended to interrupt current must have an interrupting rating at least equal to the available fault current, and the overcurrent devices, total impedance, equipment short-circuit current ratings, and protection must be selected so that the available fault current at the terminals does not exceed the equipment's withstand/short-circuit current rating.

  17. What are the standard ampere ratings for branch circuits per Article 210.3 / 240.6(A)?

    Standard branch-circuit ratings (fixed-trip) are 15, 20, 30, 40, and 50 amperes. Other standard fuse/breaker ratings include 15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, 100, 110, 125, 150, 175, 200 A, and higher.

  18. Per Article 210, what is the maximum load (continuous plus noncontinuous) permitted on a branch circuit, and how is the continuous portion treated?

    The branch-circuit rating must be at least the noncontinuous load plus 125% of the continuous load. Expressed as a formula: $$I_{circuit} \geq I_{noncontinuous} + 1.25 \times I_{continuous}$$ The total connected load must not exceed the branch-circuit rating.

  19. On a multi-outlet branch circuit, per Table 210.21(B)(2), what is the maximum load a single receptacle may serve relative to the circuit rating, and for a 20 A circuit what is the max cord-and-plug load on one receptacle of two or more?

    On a circuit supplying two or more receptacles, a single cord-and-plug-connected load on one receptacle must not exceed 80% of the receptacle rating. On a 20 A circuit, that limits one piece of equipment to $0.80 \times 20 = 16\text{ A}$.

  20. Per Article 210.8(A), name at least five locations in dwelling units where 125 V to 250 V receptacles require GFCI protection.

    GFCI protection is required for receptacles in: bathrooms, garages and accessory buildings, outdoors, crawl spaces, basements (finished and unfinished), kitchens (serving countertop and within 6 ft of a sink), laundry areas, boathouses, and areas with sinks/within 6 ft of a sink. (Any five of these.)

Show the other 41 National Electrical Code Navigation and General Requirements flashcards
  1. What is the small-appliance branch circuit requirement for dwelling kitchens per Article 210.11(C)(1) and 210.52(B)?

    At least two 20 A small-appliance branch circuits must be provided for the receptacle outlets serving the kitchen, pantry, breakfast room, dining room, or similar areas. These circuits must have no other outlets (with limited exceptions like a clock or gas-range outlet).

  2. Per Article 210.52(A), what is the spacing rule for receptacle outlets in dwelling habitable rooms (the '6-12 rule')?

    Receptacles must be placed so that no point along the floor line of any wall is more than $1.8\text{ m}$ ($6\text{ ft}$) from a receptacle, meaning receptacles are spaced no more than $3.6\text{ m}$ ($12\text{ ft}$) apart. Any wall space $0.6\text{ m}$ ($2\text{ ft}$) or wider requires a receptacle.

  3. Per Article 210.52(C), what is the maximum spacing for kitchen countertop receptacles, and which countertops require one?

    For countertops $300\text{ mm}$ ($12\text{ in}$) or wider, receptacles must be placed so no point along the wall countertop is more than $600\text{ mm}$ ($24\text{ in}$) from a receptacle (i.e., spaced no more than $1.2\text{ m}$ / $4\text{ ft}$ apart). Island and peninsula countertops have their own provisions.

  4. Per Article 210.70, where are lighting outlets with wall switch control required in dwellings?

    At least one wall-switch-controlled lighting outlet is required in every habitable room and bathroom, at outdoor entrances/exits with grade-level access, in hallways, stairways, attached garages, and detached garages with electric power, and at attics/underfloor/utility/basement spaces used for storage or containing equipment requiring servicing.

  5. Per Article 215, what minimum size must feeder conductors and the feeder overcurrent device be relative to the load?

    Feeder conductors must have an ampacity not less than the noncontinuous load plus 125% of the continuous load: $$I_{feeder} \geq I_{noncontinuous} + 1.25 \times I_{continuous}$$ and must not be smaller than required to supply the computed load per Article 220, including any required grounded (neutral) conductor.

  6. Per Article 215.2(A)(1), where the feeder supplies a single dwelling or feeder for an individual dwelling unit, what minimum feeder ampacity rule may apply, and what is the minimum overall feeder conductor size?

    Feeder conductors must be sized to the calculated load. The minimum feeder conductor size is generally not smaller than the load served; for feeders an equipment grounding conductor must be sized per 250.122 if the wiring method requires it. (120/240 V single-phase dwelling feeders may use the 83% reduction in 310.12 for the main power feeder.)

  7. Article 225 covers outside branch circuits and feeders. What is the minimum vertical clearance over a residential driveway and over a public road for overhead spans not exceeding 600 V?

    Per 225.18, minimum clearances are: $3.0\text{ m}$ ($10\text{ ft}$) above finished grade/sidewalks at the electrical service entrance, $3.7\text{ m}$ ($12\text{ ft}$) over residential property and driveways, and $5.5\text{ m}$ ($18\text{ ft}$) over public roads, streets, alleys, and areas subject to truck traffic.

  8. Per Article 225.30, how many feeders or branch circuits are generally permitted to supply a building or structure, and what is the exception?

    Generally, a building or structure may be supplied by only one feeder or branch circuit. Exceptions permit additional supplies for special conditions such as fire pumps, emergency/standby/legally required systems, parallel feeders, capacity requirements, different characteristics (voltage, phase, use), or documented conditions under engineering supervision.

  9. Per Article 230, how many service drops/laterals and sets of service-entrance conductors is a building generally permitted to have?

    A building or structure is generally permitted to be supplied by only ONE service (one set of service-entrance conductors), per 230.2, with specific exceptions for fire pumps, emergency systems, multiple occupancies, capacity, or by special permission.

  10. Per Article 230.71, what is the maximum number of service disconnecting means permitted for each service, and how must they be arranged?

    Each service disconnecting means is limited to a maximum of SIX. The 2020 and later NEC requires that two to six service disconnects be located in separate enclosures (or in a single listed assembly with separate compartments), each marked as a service disconnect. They must be grouped, and each must disconnect all ungrounded conductors with a single operation of no more than six movements of the hand.

  11. Per Article 230.79, what is the minimum rating of the service disconnecting means for a one-family dwelling?

    For a one-family dwelling, the service disconnecting means must have a rating of not less than 100 amperes, 3-wire. (For other loads, minimums are 60 A or 30 A depending on the number of circuits and load.)

  12. Per Article 230.70, where must the service disconnecting means be located?

    The service disconnecting means must be installed at a readily accessible location either outside the building/structure or inside nearest the point of entrance of the service conductors. It must not be located in bathrooms.

  13. What is the difference between 'service drop,' 'service lateral,' and 'service-entrance conductors' per Article 230 / 100?

    A service drop is the overhead service conductors from the utility (pole) to the service point at the building. A service lateral is the underground service conductors from the utility to the service point. Service-entrance conductors run from the service point (or terminal box/meter) to the service disconnecting means — overhead (SE) or underground (USE).

  14. Per Article 240.4, what is the basic rule for protecting conductors against overcurrent?

    Conductors (other than flexible cords/cables and fixture wires) must be protected against overcurrent in accordance with their ampacities as specified in 310.16 (etc.), after applying any required adjustment and correction factors, unless otherwise permitted by exceptions.

  15. State the NEC small-conductor rule (240.4(D)) — the maximum overcurrent protection for #14, #12, and #10 AWG copper conductors.

    Unless specifically permitted otherwise, overcurrent protection must not exceed: 15 A for 14 AWG copper, 20 A for 12 AWG copper, and 30 A for 10 AWG copper. (For aluminum: 15 A for 12 AWG and 25 A for 10 AWG.)

  16. Per Article 240.4(B), the 'next size up' rule, when may the next higher standard overcurrent device be used?

    The next higher standard overcurrent device rating (above the conductor ampacity) is permitted when: (1) the conductors are not part of a multi-outlet branch circuit supplying receptacles for cord-and-plug-connected portable loads, (2) the conductor ampacity does not correspond to a standard device rating, and (3) the next higher standard rating does not exceed 800 A.

  17. Per Article 240.6(A), list the standard ampere ratings for fuses and inverse time circuit breakers up to 100 A.

    15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, and 100 amperes.

  18. Per Article 240.21, where overcurrent protection is generally required for conductors, and what is the basic 'tap rule' concept?

    Overcurrent protection is generally required at the point where the conductor receives its supply (the point of supply). Tap conductors (smaller conductors connected to a larger feeder) are permitted without overcurrent protection at the tap point under specific conditions — the 10-foot tap rule (240.21(B)(1)) and 25-foot tap rule (240.21(B)(2)) being the most common.

  19. State the 10-foot tap rule conditions (Article 240.21(B)(1)).

    Tap conductors up to 10 ft long need no overcurrent device at the tap if: they do not extend beyond the equipment/enclosure they supply, their ampacity is not less than the load and not less than the rating of the device/conductors they supply, they are enclosed in a raceway (if leaving the enclosure), and the ampacity is at least 10% of the feeder overcurrent device rating protecting the larger conductor.

  20. State the 25-foot tap rule conditions (Article 240.21(B)(2)).

    Tap conductors up to 25 ft long need no overcurrent device at the tap if: the tap conductor ampacity is at least one-third (1/3) the rating of the overcurrent device protecting the feeder, they terminate in a single overcurrent device rated no more than the tap conductor ampacity, and they are protected from physical damage or enclosed in a raceway.

  21. What temperature columns appear in Table 310.16, and which one is most commonly used for terminations on equipment rated over 100 A?

    Table 310.16 has three insulation temperature columns: 60°C, 75°C, and 90°C. The 75°C column is most commonly used for equipment terminations rated over 100 A. The 90°C column is generally used only for derating/adjustment calculations, not for final termination ampacity.

  22. Per Article 310.15(C)(1), when must conductor ampacity be adjusted for the number of current-carrying conductors, and what is the adjustment factor for 4-6 conductors?

    Ampacity adjustment applies when more than 3 current-carrying conductors are bundled or in a raceway for more than $600\text{ mm}$ ($24\text{ in}$). For 4-6 current-carrying conductors, the adjustment factor is 80%; for 7-9 it is 70%; for 10-20 it is 50%.

  23. How is the neutral (grounded) conductor counted as a current-carrying conductor for ampacity adjustment per Article 310.15(E)?

    A neutral carrying only the unbalanced current from other conductors is NOT counted as current-carrying. However, the neutral of a 3-wire circuit from a 4-wire wye system, or where the major portion of the load is nonlinear (harmonic) so the neutral carries current, IS counted as a current-carrying conductor.

  24. What is the fundamental purpose distinction between 'grounding' and 'bonding' in Article 250?

    Grounding connects a system or equipment to the earth (or to a conductive body serving in place of earth) to stabilize voltage and provide a path for lightning/fault currents to ground. Bonding connects metallic parts together to establish electrical continuity and conductivity, ensuring a low-impedance fault-current path so overcurrent devices operate.

  25. Per Article 250, what are the five primary purposes of system and equipment grounding?

    (1) Limit voltages from lightning, line surges, or unintentional contact with higher-voltage lines; (2) stabilize voltage to earth during normal operation; (3) for equipment, limit voltage on metal parts to ground; (4) provide a low-impedance path to facilitate operation of overcurrent devices during a ground fault; and (5) provide a safe effective ground-fault current path.

  26. What is the definition and required characteristics of the 'effective ground-fault current path' per Article 250.4(A)(5)?

    It is an intentionally constructed, low-impedance, electrically conductive path designed to carry the maximum ground-fault current likely to be imposed from any point on the wiring system to the electrical supply source. It must facilitate the operation of the overcurrent device. The earth itself must NOT be used as the sole effective ground-fault current path.

  27. Per Article 250.50 and 250.52, name the electrodes that make up the grounding electrode system.

    All of the following present must be bonded together: metal underground water pipe (in contact with earth 10 ft or more), metal in-ground support structure (footing/Ufer), concrete-encased electrode (rebar/wire), ground ring, rod and pipe electrodes, plate electrodes, and other listed/local metal underground systems. If none are present, one or more made electrodes must be installed.

  28. Per Article 250.53(G), what is the required minimum depth of installation for a driven ground rod electrode, and what length must it be?

    A rod electrode must be at least $2.44\text{ m}$ ($8\text{ ft}$) in length and must be driven so that at least $2.44\text{ m}$ ($8\text{ ft}$) is in contact with the soil. It is typically driven vertically; if rock bottom is encountered it may be driven at up to 45 degrees or buried in a trench at least $750\text{ mm}$ ($30\text{ in}$) deep.

  29. Per Article 250.53(A)(2), what is the 'single rod' supplemental electrode rule and the 25-ohm requirement?

    A single rod, pipe, or plate electrode that does not have a resistance to ground of $25\ \Omega$ or less must be supplemented by one additional electrode. If two rods are used, they must be spaced at least $1.8\text{ m}$ ($6\text{ ft}$) apart. (Installing two rods is the common way to avoid having to measure resistance.)

  30. How is the grounding electrode conductor (GEC) sized per Table 250.66, and what is the maximum required size when connecting to a rod/pipe/plate electrode?

    The GEC is sized from Table 250.66 based on the largest ungrounded service-entrance conductor. However, per 250.66(A), the portion connecting to a rod, pipe, or plate electrode is never required to be larger than 6 AWG copper (4 AWG aluminum); to a concrete-encased electrode, never larger than 4 AWG copper; to a ground ring, not larger than the ring conductor.

  31. How is the equipment grounding conductor (EGC) sized per Table 250.122, and what governs the selection?

    The EGC is sized from Table 250.122 based on the rating or setting of the overcurrent device (fuse/breaker) ahead of the equipment, NOT the conductor size directly. Example: a 60 A circuit requires a minimum 10 AWG copper EGC; a 100 A circuit requires 8 AWG copper; a 200 A circuit requires 6 AWG copper.

  32. Per Article 250.122(B), when ungrounded conductors are increased in size (e.g., for voltage drop), what must happen to the equipment grounding conductor?

    When ungrounded conductors are increased in size from the minimum (for voltage drop or any reason), the wire-type equipment grounding conductors must be increased in size proportionally according to the circular mil area of the ungrounded conductors.

  33. Per Article 250.24, at a service, where is the grounded (neutral) conductor connected to the equipment/grounding, and what is the main bonding jumper?

    At the service, the grounded (neutral) conductor is bonded to the service equipment enclosure and the equipment grounding conductor by the MAIN BONDING JUMPER. This is the only point (in a typical system) where the neutral and ground are intentionally connected. The grounding electrode conductor also connects here.

  34. Per Article 250.28, how is the main bonding jumper (and system bonding jumper) sized?

    The main bonding jumper and system bonding jumper are sized per Table 250.102(C)(1), based on the size of the largest ungrounded service-entrance/derived conductor. Where the supply conductors exceed 1100 kcmil copper, the jumper must be at least 12.5% of the area of the largest phase conductor.

  35. Per Article 250.104(A), how must metal water piping systems in a building be bonded?

    The metal water piping system must be bonded to the service equipment enclosure, the grounded conductor at the service, the grounding electrode conductor (if of sufficient size), or to one or more grounding electrodes. The bonding jumper is sized per Table 250.102(C)(1) based on the service conductor size.

  36. Per Article 250.104(B), how is bonding of 'other metal piping' such as gas piping handled?

    Metal piping systems (e.g., gas, other) that may become energized must be bonded to the equipment grounding conductor of the circuit likely to energize the piping, the service equipment enclosure, the grounded conductor at the service, the GEC, or a grounding electrode. The bonding jumper is sized per Table 250.122 using the rating of the circuit likely to energize the piping.

  37. What is the difference between a grounded conductor, a grounding conductor, and a grounding electrode conductor per Article 100?

    A grounded conductor is a system conductor intentionally grounded — usually the neutral, normally carrying current. An equipment grounding conductor (EGC) is the conductive path connecting non-current-carrying metal parts to ground/source, normally carrying NO current. A grounding electrode conductor (GEC) connects the grounding electrode(s) to the grounded conductor and/or EGC at the service or source.

  38. Per Article 250.118, name at least four wiring methods or items recognized as equipment grounding conductors.

    Acceptable EGCs include: a copper/aluminum wire (bare or insulated); rigid metal conduit (RMC); intermediate metal conduit (IMC); electrical metallic tubing (EMT); the armor of Type AC cable; the combined metallic sheath/EGC of Type MC cable; flexible metal conduit (FMC) and liquidtight FMC under listed length/size limits; and metal raceways/cable trays meeting listing requirements.

  39. Per Article 230.42, how are service-entrance conductors sized relative to the load, including continuous loads?

    Service-entrance conductors must have an ampacity not less than the noncontinuous load plus 125% of the continuous load (or the load per 220 calculation): $$I_{SE} \geq I_{noncontinuous} + 1.25 \times I_{continuous}$$ The conductors must not be smaller than the rating of the service disconnecting means as required.

  40. Per the optional 310.12 rule, what reduced ampacity is permitted for 120/240 V, single-phase dwelling service and feeder conductors?

    For an individual dwelling unit's main power feeder or service conductors (120/240 V, 3-wire, single-phase), the conductors are permitted to have an ampacity not less than 83% of the service/feeder rating. For example, a 200 A service requires $0.83 \times 200 = 166\text{ A}$, allowing 4/0 AWG aluminum or 2/0 AWG copper at 75°C.

  41. What is the general voltage drop recommendation in the NEC for branch circuits and feeders, and is it mandatory?

    The NEC recommends (in Informational Notes, e.g., 210.19 and 215.2) that the voltage drop on a branch circuit not exceed 3%, and the combined branch circuit plus feeder not exceed 5%, of the nominal voltage for reasonable efficiency. Because it appears in Informational Notes, it is a recommendation, NOT a mandatory requirement (except in specific cases like fire pumps or sensitive equipment).

Journeyman/Master Electrician License Exam National Electrical Code Navigation and General Requirements FAQ

What is in the Journeyman/Master Electrician License Exam National Electrical Code Navigation and General Requirements syllabus?

Journeyman/Master Electrician License Exam National Electrical Code Navigation and General Requirements is split into 4 chapters: Code Structure and Administration, Branch Circuits, Feeders, and Outlets, Services and Overcurrent Protection and Grounding and Bonding. Together they contain 15 topics and 36 sub-topics.

How many chapters are in Journeyman/Master Electrician License Exam National Electrical Code Navigation and General Requirements?

4 chapters, containing 15 topics and 36 sub-topics. The largest chapter is Code Structure and Administration, with 4 topics.

Are there flashcards for Journeyman/Master Electrician License Exam National Electrical Code Navigation and General Requirements?

Yes — a 61-card National Electrical Code Navigation and General Requirements deck, printed in full in the flashcards section of this page and available in the Examius app with spaced repetition. The free plan covers one exam of your choice, including its flashcards; Examius Pro, a one-time purchase, unlocks every other exam and deck.