Plans Theme
4 topics- Purpose and levels of plan
- Project Plan, Stage Plan and Team Plan
- Exception Plan as a recovery plan after an exception
- Product-based planning technique
- Writing the project product description
- Creating the product breakdown structure
- Writing product descriptions
- Creating the product flow diagram
- The PRINCE2 approach to planning
- Designing the plan and defining/analysing products
- Identifying activities, dependencies, resources and estimates
- Scheduling, analysing risks and documenting the plan
- Plans theme responsibilities and tailoring
- Roles in producing and approving plans
- Tailoring planning to project scale and delivery method
- Purpose and levels of plan
-
Risk Theme
4 topics- Risk concepts and management approach
- Threats and opportunities; risk as uncertainty of outcome
- Risk appetite, risk tolerance and risk budget
- Risk Management Approach and Risk Register
- The risk management procedure
- Identify (context and risks)
- Assess (estimate and evaluate)
- Plan, Implement and Communicate
- Risk responses
- Threat responses: avoid, reduce, transfer, share, accept, prepare contingency
- Opportunity responses: exploit, enhance, share, reject
- Risk roles and risk ownership
- Risk owner and risk actionee distinction
- Expected monetary value and probability/impact assessment
- Risk concepts and management approach
-
Change Theme
4 topics- Change concepts and issue types
- Request for change, off-specification and problem/concern
- Baselines and the role of change control
- Change Control Approach and registers
- Issue Register and Issue Reports
- Configuration item records and product status accounts
- Issue and change control procedure
- Capture, examine, propose, decide and implement
- Formal versus informal issue handling
- Change budget and change authority
- Setting and using a change budget
- Decision thresholds and escalation of changes
- Change concepts and issue types
-
Progress Theme
4 topics- Progress concepts and tolerances
- Tolerances across the six aspects at project, stage and work package levels
- Manage by exception applied to progress
- Controls for progress
- Time-driven and event-driven controls
- Baselines, reviewing progress and capturing/reporting
- Progress reporting management products
- Checkpoint Reports and Highlight Reports
- Exception Reports and End Stage/End Project Reports
- Raising exceptions and forecasting
- Escalation when tolerances are forecast to be breached
- Use of logs and registers as progress data sources
- Progress concepts and tolerances
Project Management Professional / PRINCE2 The Practice Themes (Part 2): Plans, Risk, Change and Progress flashcards โ 60 questions with answers
What are the four levels of plan in PRINCE2 (PRINCE2 7), and which one is optional?
Project Plan, Stage Plan, and Team Plan, plus the optional Exception Plan. The Team Plan is itself optional, and the Exception Plan replaces a Project or Stage Plan that is forecast to exceed tolerances.
Define a 'plan' in PRINCE2.
A document that describes how, when and by whom a specific target (or set of targets) is to be achieved. It contains the products, activities and resources required, not just a timeline.
What is the purpose of the Project Plan?
It provides a high-level statement of how and when the project's objectives are to be achieved, showing major products, activities and resources. It is the baseline against which the Project Board monitors project progress, stage by stage.
What is the purpose of a Stage Plan and who uses it?
It provides the detailed, day-to-day basis for a single management stage, used by the Project Manager to plan and control work within that stage.
What is an Exception Plan and what does it cover?
A plan prepared to recover from the impact of a tolerance deviation. It covers the period from the present time to the end of the current stage (or project) and, once approved, replaces the plan it supersedes.
Name the four steps of PRINCE2's product-based planning technique in order.
1) Write the project product description; 2) Create the product breakdown structure; 3) Write the product descriptions; 4) Create the product flow diagram.
What is the Project Product Description and when is it first created?
A special product description for the project's overall final product (the project's main outcome). It defines what the project must deliver to gain acceptance, including acceptance criteria, and is created in the Starting Up a Project process.
What is a product breakdown structure (PBS)?
A hierarchy of all the products to be created by a plan, showing how they break down into their constituent sub-products (a hierarchy of products, not activities).
What is the difference between a product breakdown structure and a product flow diagram?
The PBS is a hierarchy showing what products are needed; the product flow diagram shows the sequence and dependencies in which those products must be created.
What does a product description contain?
The product's purpose, composition, derivation, format/presentation, development skills required, and quality criteria, quality tolerances, quality method, and quality responsibilities.
Why does PRINCE2 advocate product-based planning over activity-based planning?
Because identifying the products first focuses the plan on the required deliverables and their quality, reduces the risk of missing scope, and makes activities and dependencies easier to derive from clearly defined products.
List the typical steps of the PRINCE2 approach to planning a plan.
Design the plan; define and analyse the products (product-based planning); identify activities and dependencies; prepare estimates; prepare the schedule; document the plan; and analyse risks throughout.
In the Plans practice, who is accountable for the Project Plan versus the Stage Plan?
The Project Manager creates both, but the Project Board (Executive) approves the Project Plan, while the Project Manager produces and uses Stage Plans (approved by the Project Board at each stage boundary).
Give two examples of how the Plans practice can be tailored.
Combining the Project Plan and Stage Plan for a very short project; and varying the formality, number of stages, or planning tools (e.g., agile backlogs and sprint plans) to suit the project's scale and environment.
Define 'risk' in PRINCE2.
An uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives. A risk has a cause, an event, and an effect, and can be a threat or an opportunity.
What is the difference between a threat and an opportunity in PRINCE2 risk management?
A threat is an uncertain event that would have a negative impact on objectives; an opportunity is an uncertain event that would have a positive (favourable) impact on objectives.
What is the purpose of the Risk Management Approach document?
It describes how risk will be managed on the project, including the procedures, techniques, roles and responsibilities, tools, reporting, scales for assessing probability and impact, risk tolerances, and the format of the risk register.
Distinguish risk probability, risk impact and risk proximity.
Probability is the likelihood the risk will occur; impact is the effect on objectives if it occurs; proximity is how soon (in time) the risk is likely to materialise.
Name the five steps of the PRINCE2 risk management procedure.
Identify, Assess, Plan, Implement, and Communicate. (Communicate runs continuously alongside the other four.)
What two activities make up the 'Identify' step of the risk management procedure?
Identify the context (understand the project's objectives and the Risk Management Approach) and identify the individual risks (capturing cause, event and effect).
Show the other 40 The Practice Themes (Part 2): Plans, Risk, Change and Progress flashcards
What two sub-activities make up the 'Assess' step of the risk management procedure?
Estimate (assess probability, impact and proximity of each risk) and Evaluate (assess the net effect of all risks together on the project โ the overall risk exposure).
What is a risk owner versus a risk actionee?
A risk owner is the person responsible for the management, monitoring and control of a particular risk (including the chosen responses). A risk actionee is the person assigned to carry out a specific risk response action and supports/reports to the risk owner.
List the five threat responses in PRINCE2.
Avoid, Reduce (mitigate likelihood/impact), Transfer, Accept, and Share.
List the PRINCE2 responses to an opportunity.
Exploit, Enhance, Reject, Share, and (sometimes listed) Accept. Exploit makes the opportunity certain; enhance increases probability/impact; reject takes no action; share splits gain with another party.
What does the 'Transfer' threat response mean, and is the risk fully removed?
Transfer passes the financial impact of a threat to a third party (e.g., insurance or a contract clause). It usually addresses only the financial impact; some residual risk typically remains with the project.
What is the 'Share' risk response?
A response, applicable to both threats and opportunities, where parties share the gain (if the risk stays within agreed limits) or the pain (if it exceeds them), typically via a pain/gain formula in a contract.
What is 'risk appetite' versus 'risk tolerance'?
Risk appetite is the organisation's unique attitude towards risk-taking โ how much risk it is willing to accept. Risk tolerance is the threshold level of risk exposure which, when exceeded, triggers escalation (an exception).
What is 'inherent risk' compared with 'residual risk' and 'secondary risk'?
Inherent risk is the exposure before any response is applied; residual risk is the exposure remaining after responses are applied; secondary risk is a new risk that arises as a direct consequence of implementing a response.
How is a risk's expected monetary value calculated?
Expected value $= P \times I$, where $P$ is the probability of the risk occurring and $I$ is its monetary impact. For example, $0.2 \times \pounds50{,}000 = \pounds10{,}000$.
What is a 'risk budget'?
A sum of money set aside in the project budget specifically to fund the management responses to the project's threats and opportunities (including contingency for accepted risks).
Define an 'issue' in PRINCE2.
A relevant event that has happened, was not planned, and requires management action. Unlike a risk (which is uncertain), an issue has actually occurred.
What are the three types of issue in PRINCE2?
Request for change, Off-specification, and Problem/concern.
What is an 'off-specification'?
An issue where a product does not (or is forecast not to) meet its specification or agreed quality criteria โ i.e., something that should be provided but currently is not, or will not be.
What is a 'request for change'?
An issue proposing a modification to a baselined product or to the project's agreed scope/specification โ a proposal to change something that was previously agreed.
What does the Change Control Approach document define?
How issues and changes will be identified, assessed and controlled throughout the project โ including the procedure, the change authority, the change budget, the scales for rating severity/priority, the registers used, and the tools/roles involved.
Distinguish the Issue Register from the Daily Log for capturing issues.
Formally managed issues are recorded in the Issue Register and handled via the issue and change control procedure; minor informal issues the Project Manager handles day-to-day may simply be recorded in the Daily Log.
What is captured in the Issue Register?
Details of all formally raised issues: issue identifier, type, date raised, raised by, description, priority, severity, status, and closure details โ used to monitor and control issues throughout the project.
What is the purpose of a configuration item record (product status/asset control)?
To record information needed to manage a product, including its status, version, variant, and relationships to other products, supporting control of the project's baselined products.
Name the five steps of the issue and change control procedure.
Capture, Assess, Propose (recommend), Decide, and Implement.
In the issue and change control procedure, what happens in the 'Decide' step?
The recommended response is escalated to the appropriate authority (Project Manager within tolerance, change authority, or Project Board) who approves, rejects, or defers the proposed change or response.
What is a 'change authority' and why delegate to one?
A person or group to whom the Project Board may delegate authority to approve or reject requests for change or off-specifications, within defined limits (often funded by a change budget), to avoid overloading the Board with minor change decisions.
What is a 'change budget'?
A sum of money set aside to fund the cost of authorised requests for change (and sometimes off-specifications) during the project, allowing changes to be approved without repeatedly returning to corporate funding.
Two commonly used techniques for prioritising and grouping changes are MoSCoW and what severity concept?
MoSCoW (Must have, Should have, Could have, Won't have for now) is used for prioritisation; severity rating is used to determine the level of decision-making authority needed (e.g., Project Manager, change authority, or Project Board).
Define 'progress' in PRINCE2.
The measure of the achievement of objectives of a plan โ comparing actual achievements against the planned baseline of products, time, cost, quality, scope, benefit and risk.
What are the six (sometimes seven) tolerance areas (performance targets) in PRINCE2?
Cost, Time, Quality, Scope, Benefits and Risk (sustainability is added as a target in PRINCE2 7). Tolerance is the permissible deviation around a target before escalation is required.
What are the two main purposes of the Progress practice's controls?
To establish mechanisms to monitor and compare actual achievements against planned, and to control any unacceptable deviations โ providing the decision-making framework (delegation of tolerances, reporting, exceptions) for the project.
How does PRINCE2 use management stages to control progress?
By dividing the project into management stages separated by decision points (stage boundaries) where the Project Board reviews progress, confirms continued viability, and authorises the next stage โ implementing management by stages.
What is the difference between event-driven and time-driven controls?
Event-driven controls take place when a specific event occurs (e.g., end of a stage, completion of a product, creation of an Exception Report). Time-driven controls take place at predefined regular intervals (e.g., a Highlight Report every two weeks).
What is the purpose of a Highlight Report and who sends/receives it?
It provides the Project Board (and possibly stakeholders) with a summary of stage progress at a frequency they define. It is a time-driven report produced by the Project Manager during a stage.
What is a Checkpoint Report and how does it relate to the Highlight Report?
A Checkpoint Report is produced by a Team Manager to report team-level progress to the Project Manager at a frequency agreed in the Work Package. The Project Manager uses Checkpoint Reports as input to the Highlight Report sent to the Project Board.
What is an Exception Report and when is it produced?
It is produced by the Project Manager for the Project Board when a stage or project is forecast to exceed its agreed tolerances. It describes the exception, options, the recommendation, and the impact, allowing the Board to decide on a course of action.
What is the difference between an Exception Report and an Exception Plan?
An Exception Report alerts the Project Board to a forecast tolerance breach and recommends a way forward; an Exception Plan is the detailed replacement plan prepared (if requested by the Board) to recover from that breach.
What is the End Stage Report used for?
Produced by the Project Manager at the end of each stage, it gives the Project Board a summary of the stage's actual performance against its plan, the status of the Project Plan, Business Case and risks, and supports the decision to authorise the next stage.
What is the difference between the End Stage Report and the End Project Report?
The End Stage Report reviews one management stage and supports authorisation of the next stage; the End Project Report reviews the whole project against the original Project Initiation Documentation and supports the decision to close the project.
How do tolerances relate to escalation and 'management by exception'?
The Project Board delegates authority to the Project Manager to manage a stage within agreed tolerances. As long as work stays within tolerance, the Project Manager proceeds without referring up; if a tolerance is forecast to be exceeded, the situation must be escalated as an exception.
At which two boundaries of delegated tolerance does the Project Board itself report upward, and to whom?
If project-level tolerances are forecast to be exceeded, the Project Board escalates to corporate, programme management or the customer, since the Board manages the project within tolerances set by that higher level.
What is 'forecasting' in the context of progress control?
Using current performance data and trends to predict whether the project/stage will complete within its tolerances โ enabling deviations to be identified and escalated before they actually occur, rather than only reporting on the past.
What is the relationship between Work Packages and progress control?
A Work Package is the agreement between Project Manager and Team Manager defining the products, constraints and tolerances for a piece of work. It is a key control: progress against it is reported via Checkpoint Reports, and breaches of its tolerances are escalated to the Project Manager.
What baselines are used as the reference points for measuring progress?
The approved Project Plan, Stage Plan(s) and Work Packages serve as the baselines against which actual progress (products completed, time, cost, quality, scope, benefits, risk) is measured and forecast.
How does tailoring apply to the Progress practice for a simple project?
Controls can be made less formal โ for example fewer stages, verbal or lightweight Highlight/Checkpoint reporting, or combining reports โ provided the essential decision points, tolerances and escalation mechanisms are preserved.
Project Management Professional / PRINCE2 The Practice Themes (Part 2): Plans, Risk, Change and Progress FAQ
What is in the Project Management Professional / PRINCE2 The Practice Themes (Part 2): Plans, Risk, Change and Progress syllabus?
Project Management Professional / PRINCE2 The Practice Themes (Part 2): Plans, Risk, Change and Progress is split into 4 chapters: Plans Theme, Risk Theme, Change Theme and Progress Theme. Together they contain 16 topics and 37 sub-topics.
How many chapters are in Project Management Professional / PRINCE2 The Practice Themes (Part 2): Plans, Risk, Change and Progress?
4 chapters, containing 16 topics and 37 sub-topics. The largest chapter is Plans Theme, with 4 topics.
Are there flashcards for Project Management Professional / PRINCE2 The Practice Themes (Part 2): Plans, Risk, Change and Progress?
Yes โ a 60-card The Practice Themes (Part 2): Plans, Risk, Change and Progress deck, printed in full in the flashcards section of this page and available in the Examius app with spaced repetition. The free plan covers one exam of your choice, including its flashcards; Examius Pro, a one-time purchase, unlocks every other exam and deck.