  1. Introduction to PRINCE2 as a Method

    5 topics
    • What PRINCE2 is and what it is not
      • PRINCE2 as a non-proprietary, generic project management method (PRojects IN Controlled Environments)
      • Origins: CCTA/OGC, PROMPT II, and AXELOS/PeopleCert stewardship
      • Scope limits: aspects deliberately excluded (specialist techniques, leadership skills, detailed tools)
      • Relationship to bodies of knowledge (APM BoK, PMBOK) and to ITIL/MSP/MoP
    • Definition and characteristics of a project
      • Project as a temporary organisation created to deliver business products
      • Five characteristics: change, temporary, cross-functional, unique, uncertainty
      • Distinguishing projects from business-as-usual operations
    • The six aspects of project performance to be managed
      • Cost, timescales, quality, scope, benefits (outcomes), risk
      • How tolerances are set against each aspect
    • The integrated elements of PRINCE2
      • Principles, themes, processes and the project environment
      • How the four elements interlock to form a complete method
    • Benefits of adopting PRINCE2
      • Common vocabulary and consistency across projects
      • Manage-by-exception efficiency for senior management
      • Reusable, scalable framework recognised across UK public and private sectors
  2. Customer/Supplier Context and Stakeholders

    3 topics
    • The customer/supplier environment assumption
      • Customer who commissions and pays; supplier who provides skills and resources
      • Single or multiple suppliers, internal or commercial relationships
    • Categories of stakeholder
      • Business, user and supplier interests
      • External stakeholders and influencers
    • Programmes and portfolios as context
      • Projects sitting within MSP programmes and MoP portfolios
      • Corporate or commissioning management as the project's host
  3. Tailoring and Adopting PRINCE2

    4 topics
    • Tailoring versus embedding
      • Tailoring by a project team to suit a specific project
      • Embedding by an organisation to adopt PRINCE2 as standard
    • What can be tailored
      • Processes, themes, roles, management products and terminology
      • Combining roles and adjusting management product formats
    • Factors influencing tailoring
      • Project scale, complexity, importance, capability and risk
      • Agile delivery contexts and PRINCE2 Agile considerations
    • Documenting tailoring decisions
      • Recording in the PID and tailoring section
      • Avoiding the danger of un-tailored or over-bureaucratic application

Project Management Professional / PRINCE2 PRINCE2 Foundations, Overview and the Project Environment flashcards โ€” 51 questions with answers

  1. What does the acronym PRINCE2 stand for?

    PRojects IN Controlled Environments (version 2).

  2. How is PRINCE2 best described as a method?

    It is a structured, process-based, generic project management method that can be tailored and applied to any type or size of project regardless of industry, geography or culture.

  3. Name three things PRINCE2 is NOT (its deliberate exclusions).

    PRINCE2 is not: (1) a set of specialist/technical delivery techniques, (2) leadership capability or interpersonal skills, and (3) detailed tools, templates or contracting/procurement methods.

  4. PRINCE2's definition of a project: what is a project?

    A temporary organization that is created for the purpose of delivering one or more business products according to an agreed business case.

  5. List the five characteristics that distinguish project work from business-as-usual.

    Change, Temporary, Cross-functional, Unique, and Uncertainty.

  6. Why is a project described as 'temporary'?

    Because it has a defined start and a defined end; once the desired change has been delivered, business-as-usual resumes and the temporary project organization is disbanded.

  7. List the six aspects (variables/tolerances) of project performance that must be managed in PRINCE2.

    Costs, Timescales, Quality, Scope, Benefits and Risk.

  8. In the six aspects of performance, which aspect answers 'How good?' and which answers 'How much?'

    Quality answers 'How good (must the products be / fit for purpose)?' and Scope answers 'How much (what will be delivered)?'.

  9. Which of the six performance aspects answers the question 'Why?' (the project's justification)?

    Benefits โ€” the reasons for doing the project and the measurable improvements expected.

  10. Which performance aspect addresses 'How achievable?' and concerns uncertainty?

    Risk โ€” managing the uncertainties (threats and opportunities) that could affect the project's objectives.

  11. List the four integrated elements of PRINCE2.

    Principles, Themes, Processes, and the Project Environment (tailoring PRINCE2 to the project environment).

  12. What is the role of the seven PRINCE2 principles?

    They are the guiding obligations and good practices, derived from successful and failed projects, that determine whether a project is genuinely being managed using PRINCE2; they are universal, self-validating and empowering.

  13. List the seven PRINCE2 principles.

    Continued business justification; Learn from experience; Defined roles and responsibilities; Manage by stages; Manage by exception; Focus on products; and Tailor to suit the project.

  14. What do the PRINCE2 'themes' describe?

    Aspects of project management that must be addressed continually and in parallel throughout the project (the 'what' and 'why' that must be set up and kept active).

  15. List the seven PRINCE2 themes.

    Business Case, Organization, Quality, Plans, Risk, Change, and Progress.

  16. What do the PRINCE2 'processes' describe?

    A progression through the project lifecycle โ€” the activities, with their recommended inputs and outputs, needed to direct, manage and deliver a project successfully (the 'who does what and when').

  17. List the seven PRINCE2 processes.

    Starting up a Project (SU), Directing a Project (DP), Initiating a Project (IP), Controlling a Stage (CS), Managing Product Delivery (MP), Managing a Stage Boundary (SB), and Closing a Project (CP).

  18. State at least four key benefits of adopting PRINCE2.

    It is generic/best practice and widely understood; provides a common vocabulary; ensures continued business justification; gives controlled, organized start, middle and end; provides regular reviews against plan and business case; enables manage-by-exception (efficient senior use of time); involves stakeholders at the right time; and promotes learning and continual improvement.

  19. How does PRINCE2 promote effective communication among project participants?

    By providing a common structure, vocabulary and set of defined roles, so all participants share a consistent understanding of the project and the language used to describe it.

  20. State the customer/supplier environment assumption underlying PRINCE2.

    PRINCE2 assumes there will be a customer who specifies the desired result and (usually) pays for the project, and a supplier who provides the resources and skills to deliver that result.

Show the other 31 PRINCE2 Foundations, Overview and the Project Environment flashcards
  1. In the customer/supplier model, define the 'customer' and the 'supplier'.

    The customer is the person/group who commissions the work, will benefit from the results and typically pays for the project. The supplier is the person/group who provides the specialist resources and skills required to deliver the project's products.

  2. Why does PRINCE2 base its model on a customer/supplier relationship even within a single organization?

    Because the same dynamic exists internally: one part of the organization (customer) commissions and funds the work while another part (supplier) provides the resources to create the products, ensuring both interests are represented.

  3. Define a 'stakeholder' in the PRINCE2 context.

    Any individual, group or organization that can affect, be affected by, or perceive itself to be affected by the project.

  4. PRINCE2 groups the principal interests/stakeholders into which three categories?

    Business, User, and Supplier.

  5. What interest does the 'Business' stakeholder category represent?

    It ensures the project delivers value for money โ€” the project remains worth the investment and the business case is sound (represented by the Executive).

  6. What interest does the 'User' stakeholder category represent?

    Those who will use the project's products to realize benefits, or who will operate/maintain or be impacted by them; they specify needs and ensure the solution meets them (represented by Senior User(s)).

  7. What interest does the 'Supplier' stakeholder category represent?

    Those providing the skills and resources to create the products; they ensure products are delivered to the required quality (represented by Senior Supplier(s)).

  8. Define a 'programme' as the context for a PRINCE2 project.

    A temporary, flexible organization created to coordinate, direct and oversee the implementation of a set of related projects and activities in order to deliver outcomes and benefits related to a set of strategic objectives.

  9. Define a 'portfolio' as the context for a PRINCE2 project.

    The totality of an organization's investment (or a segment of it) in the changes required to achieve its strategic objectives โ€” i.e. all the programmes and projects undertaken to meet strategy.

  10. How can a PRINCE2 project sit within a wider organizational context?

    A project may be standalone, part of a programme, and/or part of a portfolio; when within a programme/portfolio, some management activities (e.g. business case, assurance, governance) may be set or supported at the programme/portfolio level.

  11. In PRINCE2, define 'tailoring'.

    Adapting the method to suit the project's context โ€” its scale, complexity, importance, team capability and risk โ€” for example by adjusting themes, terminology, roles and management products to the specific project.

  12. In PRINCE2, define 'embedding'.

    What an organization does to adopt PRINCE2 across all of its projects โ€” standardizing its use through process integration, standards, training, tools and assurance (embedding is done by the organization; tailoring is done by the project).

  13. State the key difference between tailoring and embedding.

    Tailoring is performed by the project management team and relates to a single project; embedding is performed by the organization and relates to adopting PRINCE2 across all of its projects.

  14. What is the purpose of tailoring PRINCE2?

    To ensure the method matches the project's environment and that the project controls are appropriate to the project's scale, complexity, importance, capability and risk โ€” avoiding both robotic over-application and unsafe under-application.

  15. List the main things that can be tailored in PRINCE2.

    The processes (combined or adapted), the themes (applied via management products), the management products (combined, split or renamed), the roles (combined or split), the terminology, and the use of tolerances โ€” but not the seven principles.

  16. Which integrated element of PRINCE2 must NOT be tailored or omitted?

    The seven principles โ€” they must always be applied; if they are not, the project is not being run as a PRINCE2 project.

  17. When tailoring management products, what are the options?

    Management products can be combined, split, renamed, presented in different formats (e.g. document, presentation, conversation, data entry) or aligned to existing organizational standards, provided their purpose is still fulfilled.

  18. How may PRINCE2 roles be tailored?

    Roles can be combined (e.g. one person holding several roles) or split (a role shared among several people), but the accountabilities defined for each role must still be assigned and not lost.

  19. List several factors that influence how a project should be tailored.

    The project's scale, complexity, importance/risk, the type of project (e.g. lifecycle/agile/sequential), team capability and maturity, geography and culture, commercial/contractual context, and whether the project sits within a programme or portfolio.

  20. How does whether a project is part of a programme or portfolio influence tailoring?

    The programme/portfolio may impose standards, terminology, reporting, assurance and governance that the project must align with, so the project tailors PRINCE2 to fit the wider framework rather than defining everything independently.

  21. Why must tailoring decisions be documented, and where are they recorded?

    To ensure decisions are deliberate, justified, communicated and agreed โ€” preventing inappropriate omission of controls. They are typically recorded in the Project Initiation Documentation (PID), often within a tailoring section, and may reference organizational standards.

  22. Which management product captures the overall approach to tailoring PRINCE2 for a specific project?

    The Project Initiation Documentation (PID) โ€” it documents how the method (processes, themes, roles, management products) has been tailored for that project.

  23. Who is responsible for ensuring PRINCE2 is appropriately tailored for a project?

    The Project Manager (with the Project Board's approval), guided by any organizational/programme standards and supported by project assurance.

  24. What is the risk of NOT tailoring PRINCE2 ('robotic' application)?

    Applying the method without thought leads to 'robotic' project management โ€” excessive bureaucracy and effort with no added value โ€” or, if controls are wrongly omitted, to 'PINO' (PRINCE2 In Name Only).

  25. What is meant by 'PINO' in the context of tailoring?

    PRINCE2 In Name Only โ€” claiming to use PRINCE2 while failing to apply its principles, so the method's benefits are not actually achieved.

  26. Distinguish 'outputs', 'outcomes' and 'benefits' as used around the benefits aspect.

    An output is a specialist product delivered by the project; an outcome is the result of the change derived from using the outputs; a benefit is the measurable improvement resulting from an outcome that is perceived as an advantage by stakeholders.

  27. Why is 'continued business justification' so central to PRINCE2's value proposition?

    Because it ensures there is always a justifiable reason to start the project and that justification remains valid throughout; if continued justification is lost, the project should be stopped, protecting the organization's investment.

  28. How does PRINCE2 distinguish 'management products' from 'specialist products'?

    Management products are created for the purpose of managing the project (e.g. plans, reports, registers) and are used by PRINCE2 itself; specialist products are the actual deliverables the project is set up to produce for the customer.

  29. What does 'generic' mean as a benefit/characteristic of PRINCE2?

    PRINCE2 is independent of industry, sector, technology and project type, so it can be applied to any project and integrated with specialist/technical delivery models or other frameworks.

  30. In tailoring, what does adjusting 'tolerances' refer to?

    Setting the permitted deviation (for cost, time, quality, scope, benefits and risk) appropriate to the project's size and risk, so that manage-by-exception escalation triggers are suited to that project's context.

  31. Summarize the relationship between principles, themes, processes and tailoring in one sentence.

    The principles are mandatory and unchangeable; they are applied through the themes (continually addressed aspects) within the processes (lifecycle activities), all of which are tailored to suit each project's environment.

Project Management Professional / PRINCE2 PRINCE2 Foundations, Overview and the Project Environment FAQ

What is in the Project Management Professional / PRINCE2 PRINCE2 Foundations, Overview and the Project Environment syllabus?

Project Management Professional / PRINCE2 PRINCE2 Foundations, Overview and the Project Environment is split into 3 chapters: Introduction to PRINCE2 as a Method, Customer/Supplier Context and Stakeholders and Tailoring and Adopting PRINCE2. Together they contain 12 topics and 28 sub-topics.

How many chapters are in Project Management Professional / PRINCE2 PRINCE2 Foundations, Overview and the Project Environment?

3 chapters, containing 12 topics and 28 sub-topics. The largest chapter is Introduction to PRINCE2 as a Method, with 5 topics.

Are there flashcards for Project Management Professional / PRINCE2 PRINCE2 Foundations, Overview and the Project Environment?

Yes โ€” a 51-card PRINCE2 Foundations, Overview and the Project Environment deck, printed in full in the flashcards section of this page and available in the Examius app with spaced repetition. The free plan covers one exam of your choice, including its flashcards; Examius Pro, a one-time purchase, unlocks every other exam and deck.