🇬🇧 Association for Project Management Qualification (APM PMQ) · subject
Association for Project Management Qualification (APM PMQ) Planning for Success Syllabus
The Planning for Success syllabus for Association for Project Management Qualification (APM PMQ) in full: 4 chapters, 19 topics and 27 sub-topics, every one listed below, plus 52 Planning for Success flashcards with answers.
Planning for Success syllabus: all 4 chapters
Expand any chapter to see its topics and sub-topics.
-
Scope Management
5 topics- Defining and managing scope
- Product scope versus project scope
- Scope creep and its control
- Product breakdown structure (PBS)
- Work breakdown structure (WBS)
- Decomposing work into work packages
- Work package definitions and ownership
- Cost and organisational breakdown structures
- Cost breakdown structure (CBS)
- Organisational breakdown structure (OBS)
- Responsibility assignment matrix (RAM/RACI)
- Requirements management and benefits mapping
- Defining and managing scope
-
Scheduling and Resource Management
5 topics- Estimating techniques
- Analogous (comparative) and parametric estimating
- Bottom-up and three-point estimating
- The estimating funnel and improving accuracy
- Critical path analysis
- Network diagrams and activity dependencies
- Forward and backward pass, float and critical path
- Gantt charts and milestones
- Bar charts for communicating the schedule
- Milestone planning and tracking
- Critical chain and buffer management
- Resource management
- Resource smoothing versus resource levelling
- Resource scheduling and constraints
- Estimating techniques
-
Budgeting and Cost Control
5 topics- Developing the project budget
- Cost types: fixed, variable, direct, indirect
- Aggregating estimates into a budget
- Contingency and management reserves
- Distinguishing contingency from management reserve
- Linking contingency to risk
- Cost phasing and cash flow
- Time-phased budgets and the cumulative cost (S) curve
- Cost baselining and the funding profile
- Cost monitoring and forecasting
- Developing the project budget
-
Quality Management
4 topics- Quality planning
- Quality criteria and acceptance criteria
- The quality management plan
- Quality control versus quality assurance
- Inspection and testing (control)
- Process audits and assurance
- Continual improvement
- Plan-Do-Check-Act (Deming) cycle
- Lessons learned and process improvement
- Cost of quality
- Quality planning
Association for Project Management Qualification (APM PMQ) Planning for Success flashcards — 52 questions with answers
In APM project planning, what is 'scope' and what does scope management involve?
Scope is the totality of the outputs, outcomes and benefits, and the work required to produce them. Scope management is the process of identifying, defining and controlling all the work needed to deliver the project, ensuring that only the agreed work (no more, no less) is carried out.
What is 'scope creep' and how is it controlled?
Scope creep is the uncontrolled, incremental expansion of project scope without corresponding adjustments to time, cost and resources. It is controlled through robust change control / configuration management and a clearly baselined scope.
What is a Product Breakdown Structure (PBS)?
A hierarchical, deliverable-oriented structure that breaks the project's final product down into its constituent sub-products or deliverables. It defines WHAT is to be produced, not the work, and is typically created before the WBS.
What is a Work Breakdown Structure (WBS) and what is a 'work package'?
A WBS is a hierarchical decomposition of the total scope of work into progressively smaller, more manageable elements. The lowest level is the work package — the smallest unit of work that can be assigned, estimated, scheduled and controlled.
What is the difference between a PBS and a WBS?
A PBS is product/deliverable oriented and shows the components of the final product (the 'what'). A WBS is work oriented and shows the activities/work packages needed to create those products (the 'how/work'). The PBS usually feeds the WBS.
What is a Cost Breakdown Structure (CBS)?
A hierarchical breakdown of a project into cost elements, mapping the costs associated with each component of the WBS/PBS. It allows costs to be aggregated and controlled against the structure of the work.
What is an Organisational Breakdown Structure (OBS) and how does it relate to the WBS?
An OBS is a hierarchical model showing the organisational structure and reporting relationships responsible for the project's work. Intersecting the OBS with the WBS produces the Responsibility Assignment Matrix (RAM), linking work packages to responsible parties.
What is a Responsibility Assignment Matrix (RAM) and a common form of it?
A RAM maps WBS work packages to the OBS to show who is responsible for each element of work. A common form is the RACI chart, identifying who is Responsible, Accountable, Consulted and Informed for each task.
In requirements management, distinguish between a project's outputs, outcomes and benefits.
Outputs are the tangible deliverables/products created. Outcomes are the changed circumstances or capabilities resulting from using the outputs. Benefits are the measurable improvements arising from the outcomes that are perceived as advantageous by stakeholders.
What is requirements management?
The process of capturing, analysing, documenting, prioritising, agreeing and controlling stakeholder requirements throughout the project, ensuring the solution delivered meets the agreed needs.
What is a benefits map (benefits mapping)?
A diagram that shows the logical links between project outputs, the enabling and business changes, the resulting outcomes, and the end benefits and objectives. It demonstrates how delivering outputs leads to the realisation of benefits.
What is the difference between estimating accuracy at concept stage versus a definitive estimate?
Early (concept/order-of-magnitude) estimates have wide tolerances (e.g. roughly $-25\%$ to $+75\%$) because little is known. Definitive estimates, made later with detailed information, are far more accurate (e.g. roughly $\pm 5\%$ to $\pm 10\%$).
What is the difference between top-down (analogous) and bottom-up estimating?
Top-down (analogous) estimating uses data from similar past projects to estimate the whole quickly but less accurately. Bottom-up estimating sums detailed estimates of each individual work package, giving greater accuracy but requiring more time and detailed information.
What is parametric estimating?
An estimating technique that uses a statistical or mathematical relationship between historical data and other variables (e.g. cost per square metre, cost per line of code) to calculate an estimate.
What is the 'estimating funnel'?
The concept that estimate accuracy improves as the project progresses and more information becomes known. The range of uncertainty is wide at the start and narrows (like a funnel) as the project moves through its life cycle.
What is comparative (analogous) estimating based on?
It is based on comparison with similar previous projects or work, scaling their actual data to produce an estimate for the current project. It relies on the availability of relevant historical information.
What is the three-point estimating formula for the expected (PERT/beta) duration?
$$t_E = \frac{O + 4M + P}{6}$$ where $O$ = optimistic, $M$ = most likely, and $P$ = pessimistic estimate.
In three-point (PERT) estimating, how are the standard deviation and variance of an activity calculated?
$$\sigma = \frac{P - O}{6}, \qquad \text{Variance} = \sigma^{2} = \left(\frac{P - O}{6}\right)^{2}$$ where $P$ = pessimistic and $O$ = optimistic estimate.
What is critical path analysis (CPA)?
A network-based scheduling technique that identifies the sequence of dependent activities (the critical path) that determines the shortest possible project duration. Any delay to a critical activity delays the whole project.
What is the critical path of a project network?
The longest path of dependent activities through the network, which determines the minimum project duration. Activities on it have zero total float.
Show the other 32 Planning for Success flashcards
How are early start (ES) and early finish (EF) calculated in a forward pass?
$$EF = ES + \text{Duration}$$ The ES of an activity is the latest EF of its predecessors. The forward pass works left to right from the start, taking the maximum where activities merge.
How are late finish (LF) and late start (LS) calculated in a backward pass?
$$LS = LF - \text{Duration}$$ The LF of an activity is the earliest LS of its successors. The backward pass works right to left from the end, taking the minimum where activities merge.
What is total float and how is it calculated?
Total float is the amount of time an activity can be delayed without delaying the project end date. $$\text{Total Float} = LS - ES = LF - EF$$
What is free float?
The amount of time an activity can be delayed without delaying the early start of any immediately following (successor) activity. It is calculated as the earliest ES of successors minus the EF of the activity.
What is a Gantt chart and what is its main strength?
A Gantt (bar) chart is a horizontal bar chart showing activities against a timeline, with bar length representing duration. Its strength is presenting the schedule in an easily understood visual form; linked Gantt charts can also show dependencies.
What is a milestone in a project schedule?
A key event or point in time of particular significance (e.g. a phase completion, gate review or major deliverable handover) that has zero duration and is used to monitor and report progress.
What is the difference between Critical Path Method and Critical Chain in handling resources?
Critical Path Method assumes resources are unlimited and focuses on logical dependencies. Critical Chain considers both task dependencies and resource constraints, identifying the longest resource-constrained path through the project.
What is the critical chain?
The longest sequence of dependent activities through a project that takes into account both logical dependencies and resource availability/constraints. It is the resource-constrained equivalent of the critical path.
In critical chain method, what is a 'project buffer' and where is it placed?
A project buffer is a block of contingency time aggregated from individual task safety margins, placed at the end of the critical chain (before the project end date) to protect the overall completion date against variation in critical chain tasks.
In critical chain method, what are 'feeding buffers'?
Time buffers placed where a non-critical (feeding) chain of activities joins the critical chain, protecting the critical chain from delays in the feeding paths.
In critical chain, what is a 'resource buffer'?
A warning or alert (not time) placed on the critical chain to ensure that the resources needed for critical chain activities are made available on time, e.g. by alerting a resource that its task is about to begin.
What is resource management in projects, and what are its two key sub-processes?
Resource management is the acquisition and deployment of the resources (people, equipment, materials, money) needed to deliver the project. Its two key sub-processes are resource smoothing and resource levelling.
What is the difference between resource smoothing and resource levelling?
Resource smoothing uses available float to adjust activities within the existing project end date, keeping the deadline fixed while staying within resource limits. Resource levelling delays activities (using and beyond float) to stay within resource limits, which may extend the project end date.
What is a resource histogram?
A bar chart showing the amount of a given resource required against time, used to identify peaks, troughs and over-allocation so the schedule can be smoothed or levelled.
How is a project budget developed and what does it represent?
The budget is developed by aggregating the cost estimates of all work packages (bottom-up), then adding contingency and management reserves. It represents the total authorised funds allocated to deliver the project.
What is the difference between the cost estimate, the project budget and the cost baseline?
The estimate is the predicted cost of the work. The cost baseline is the time-phased budget against which performance is measured (estimates plus contingency reserve). The total budget adds management reserve on top of the cost baseline.
What is the difference between contingency reserve and management reserve?
Contingency reserve covers identified ('known unknown') risks and is part of the cost baseline, controlled by the project manager. Management reserve covers unidentified ('unknown unknown') risks, sits outside the cost baseline, and is controlled by the sponsor/governance.
How is contingency typically estimated?
Contingency is typically derived from quantitative risk analysis (e.g. expected monetary value of identified risks, or Monte Carlo simulation outputs at a chosen confidence level) rather than an arbitrary percentage.
What is cost phasing and what is the typical shape of cumulative project cost?
Cost phasing is the spreading of budgeted costs across the project timeline to show when money will be spent. Cumulative spend typically follows an 'S-curve' — slow at first, steeper in the middle, and tailing off near completion.
What is cash flow in a project context and why is cash flow forecasting important?
Cash flow is the movement of money in (income/funding) and out (expenditure) of the project over time. Forecasting it is important to ensure sufficient funds are available to pay for work as it occurs and to avoid funding shortfalls.
What is the cost baseline used for?
The time-phased cost baseline is the approved spend profile against which actual costs and earned value are measured and controlled. It enables variance analysis and forecasting throughout the project.
What is a funding profile and how does it relate to the spend (cost) profile?
The funding profile is the schedule of when funds (cash) are made available to the project, often released in steps or tranches at gates. It must be reconciled with the spend profile to ensure funding is available ahead of expenditure.
What does cost monitoring involve during delivery?
Cost monitoring involves recording actual costs and committed costs, comparing them against the cost baseline, analysing variances, and reporting the project's financial status to enable corrective action.
In earned value, what is Cost Variance (CV) and how is it calculated?
Cost Variance measures cost performance: $$CV = EV - AC$$ where $EV$ = earned value and $AC$ = actual cost. A positive CV is under budget; negative is over budget.
What is the Cost Performance Index (CPI) and how is it interpreted?
$$CPI = \frac{EV}{AC}$$ $CPI > 1$ means under budget (good cost efficiency); $CPI < 1$ means over budget; $CPI = 1$ means on budget.
What is Schedule Variance (SV) and the Schedule Performance Index (SPI)?
$$SV = EV - PV, \qquad SPI = \frac{EV}{PV}$$ where $PV$ = planned value. Positive SV / $SPI > 1$ means ahead of schedule; negative SV / $SPI < 1$ means behind schedule.
What is the Estimate at Completion (EAC) using the CPI method?
$$EAC = \frac{BAC}{CPI}$$ where $BAC$ is the Budget at Completion. This forecasts the total expected cost assuming current cost performance continues.
What is the Estimate to Complete (ETC) and Variance at Completion (VAC)?
$$ETC = EAC - AC, \qquad VAC = BAC - EAC$$ ETC is the forecast cost of remaining work; VAC is the forecast over/under spend at the end (positive = under budget).
What is quality planning?
The process of determining the quality standards relevant to the project, defining how they will be met, and documenting them in a quality management plan — covering acceptance criteria, quality control and quality assurance activities.
Distinguish between quality control (QC) and quality assurance (QA).
Quality control is product-oriented: inspecting, testing and measuring deliverables to verify they meet acceptance criteria (detecting defects). Quality assurance is process-oriented: providing confidence that processes are appropriate and being followed correctly (preventing defects), often via independent audit.
What is continual (continuous) improvement and a common model used for it?
Continual improvement is the ongoing effort to incrementally improve processes, products and services. A common model is the Deming/Shewhart PDCA cycle — Plan, Do, Check, Act — repeated iteratively.
What are the four categories that make up the cost of quality?
Cost of conformance: (1) prevention costs and (2) appraisal/inspection costs. Cost of non-conformance: (3) internal failure costs (defects found before delivery) and (4) external failure costs (defects found by the customer after delivery).
Association for Project Management Qualification (APM PMQ) Planning for Success FAQ
What is in the Association for Project Management Qualification (APM PMQ) Planning for Success syllabus?
Association for Project Management Qualification (APM PMQ) Planning for Success is split into 4 chapters: Scope Management, Scheduling and Resource Management, Budgeting and Cost Control and Quality Management. Together they contain 19 topics and 27 sub-topics.
How many chapters are in Association for Project Management Qualification (APM PMQ) Planning for Success?
4 chapters, containing 19 topics and 27 sub-topics. The largest chapter is Scope Management, with 5 topics.
Are there flashcards for Association for Project Management Qualification (APM PMQ) Planning for Success?
Yes — a 52-card Planning for Success deck, printed in full in the flashcards section of this page and available in the Examius app with spaced repetition. The free plan covers one exam of your choice, including its flashcards; Examius Pro, a one-time purchase, unlocks every other exam and deck.